Decision and Order - Shell Energy North America (Canada) Inc. (M12531)
IN THE MATTER OF A REQUEST by SHELL ENERGY NORTH AMERICA (CANADA) INC. to cancel its Gas Marketer License...
Decision - Steve R. Murphy's Auto Services Ltd. and WSK Investments Limited (M11978)
The Board has issued its decision on an application from Steve R. Murphy's Auto Services Ltd. and WSK Investments Ltd., requesting an investigation into whether current wholesale margins for gasoline and diesel are just and reasonable. The Board has decided:
- that the wholesale margin shall remain unchanged, and that the key issue can be better addressed by adjusting the clean fuel adjustor.
- to approve a revised methodology for calculating the clean fuel adjustor. It will take effect on January 9, 2026.
- that the clean fuel adjustor amounts will be reviewed after December 31, 2026, unless otherwise ordered by the Board.
Decision and Interim Order - Petroleum Products Pricing (M12176)
IN THE MATTER OF AN ORDER made by the Board under s. 24A(2) of the Petroleum Products Pricing Regulations about the sufficiency of the current retail mark-up for self-service and full-service gasoline and diesel...
Order, and Decision Letter - Petroleum Products Pricing Regulations - Wholesale Margin for Gasoline and Diesel (M10853)
IN THE MATTER OF AN INVESTIGATION by the Board under s.24(1) of Petroleum Products Pricing Regulations about whether the current wholesale margin for gasoline and diesel is just and reasonable...
Order - GO - Petroleum Products Pricing Wholesale Margin Review (M10853)
IN THE MATTER OF AN INVESTIGATION by the Board under s. 24(1) of the Petroleum Products Pricing Regulations about whether the current wholesale margin for gasoline and diesel is just and reasonable...
All Other Decisions
Order - Eastward Energy Inc. (M12620)
IN THE MATTER OF AN APPLICATION by EASTWARD ENERGY INC. for a PERMIT TO CONSTRUCT FACILITIES TO DELIVER NATURAL GAS IN AREAS OF Halifax Regional Municipality, Nova Scotia...
Order - Eastward Energy Inc. (M12621)
IN THE MATTER OF AN APPLICATION by EASTWARD ENERGY INC. for a PERMIT TO CONSTRUCT FACILITIES TO DELIVER NATURAL GAS IN AREAS OF Cumberland County, Nova Scotia...
Order - Eastward Energy Inc. (M12622)
IN THE MATTER OF AN APPLICATION by EASTWARD ENERGY INC. for a PERMIT TO CONSTRUCT FACILITIES TO DELIVER NATURAL GAS IN AREAS OF Pictou County, Nova Scotia...
Decision - Town of Mahone Bay (M12642)
IN THE MATTER OF AN APPLICATION by the TOWN OF MAHONE BAY on behalf of its electric utility, for the approval of a rate rider to recover deferred revenue from the phasing in of the utility's last general rate increase...
Interim Order - Nova Scotia Power Incorporated (M12640)
IN THE MATTER OF AN APPLICATION by NOVA SCOTIA POWER INCORPORATED for approval to renew its existing Fuel Adjustment Mechanism (FAM) AA rider and BA rider on an interim basis effective January 1, 2026...
Decision - EfficiencyOne (M12249)
IN THE MATTER OF AN APPLICATION by EFFICIENCYONE for approval of the 2025 DSM Extension for Demand-Side Management Activities between EfficiencyOne and Nova Scotia Power Inc., and for Approval of the Amendment to the 2023-2025 Demand-Side Management Purchase Agreement between EfficiencyOne and Nova Scotia Power Inc....
Decision - Nova Scotia Power Incorporated (M12178)
IN THE MATTER OF AN APPLICATION by NOVA SCOTIA POWER INCORPORATED about asset disposition relating to the Smart Grid Nova Scotia Project, including deferral of the unrecovered net book value costs of $1.7 million over an amortization period of five years and revisions to the Solar Garden Rate Rider...
Decision and Order - Nova Scotia Power Incorporated (M12499)
IN THE MATTER OF AN APPLICATION by NOVA SCOTIA POWER INCORPORATED for approval of 2025/2026 Time-Varying Pricing Tariffs...
Decision - EfficiencyOne (M12282)
IN THE MATTER OF AN APPLICATION by EFFICIENCYONE for approval of a New Benefit-Cost Analysis Test for Evaluating Demand Side Management Plans...
Order - Nova Scotia Power Incorporated (M12184)
IN THE MATTER OF an application by NOVA SCOTIA POWER INCORPORATED for approval of a third term for the Extra Large Industrial Active Demand Control Tariff...
Decision - NSPI Maritime Link Inc. (M12285)
The Board has approved an application by NSP Maritime Link Inc., the company operating the Maritime Link, which carries renewable electricity to Nova Scotia from the Muskrat Falls hydroelectric plant in Newfoundland and Labrador, to spend an estimated $33 million to protect its underwater cables.
The approval is subject to reporting directives and final costs being confirmed in a compliance filing.